Topic 15 · Regulations & Reporting
Set B Questions 11 to 20
- 11
What does the abbreviation AHJ stand for?
Explanation
The AHJ can require more than any published minimum, and frequently does based on local experience.
- 12
Can an authority require more than the minimum?
Explanation
Local incidents and local rules both drive requirements above the national tables.
- 13
What normally happens when an assembly fails its test?
Explanation
Some purveyors require notification within a set number of days, and some can shut the service off.
- 14
What can a purveyor do if an assembly is never tested?
Explanation
Service discontinuation is the ultimate sanction in most cross-connection control programmes.
- 15
Who is responsible for maintaining an assembly?
Explanation
The purveyor requires it, the owner provides and maintains it, and the tester verifies it.
- 16
What is the purpose of a cross-connection control survey?
Explanation
The survey finds the hazards. Testing comes afterwards, once the right assemblies are in place.
- 17
Which credential covers carrying out a survey?
Explanation
Testers often add the surveyor credential later, because the two roles sit naturally together.
- 18
What does the Safe Drinking Water Act require of public systems?
Explanation
The federal framework sets the obligation. The detail of how it is met is decided at state and local level.
- 19
Why do requirements differ so much between states?
Explanation
The test criteria barely change. What changes is who certifies, how often, and which report form is accepted.
- 20
What must a tester do when the assembly is the wrong type?
Explanation
The report is the obligation. The remedy is decided by the owner and the authority having jurisdiction.