Topic 14 · Study plan and project management
Set B Questions 11 to 20
- 11
A Gantt chart is a highly critical visual project management tool explicitly designed to:
Explanation
A Gantt chart uses horizontal bars representing task durations plotted over calendar time. It maps dependencies (Task B cannot start until Task A ends) and is essential for monitoring chronological progress.
- 12
Which of the following elements must explicitly be prepared and meticulously finalized BEFORE field data collection begins?
Explanation
You must build "dummy tables" (the data analysis plan) BEFORE data collection. If you collect data without knowing exacty how you will analyze it, you will likely forget to collect critical variables entirely.
- 13
A postgraduate student formally planning a massive community-based thesis must proactively ensure which of the following logistical steps?
Explanation
Project planning for a thesis involves pure science (Sample Size), strict administrative regulations (Ethics Clearance), and brutal logistical realities (Transportation/Budget).
- 14
Which chronological stage is literally the most appropriate time to define exactly who is responsible for data cleaning?
Explanation
Roles, duties, and analytical responsibilities MUST be rigidly bound into the written protocol during the pure planning phase to prevent internal conflict and data mishandling later.
- 15
Which statement is FALSE regarding multi-centric research project implementation?
Explanation
SOPs (Standard Operating Procedures) are the undisputed lifeline of multi-centric studies. If 5 different hospitals measure blood pressure 5 intimately different ways (violating SOPs), the combined data is scientifically worthless.
- 16
In the rigid 'Research cycle', which critical step conceptually lies immediately between formulating the study objectives and practically preparing the data collection instruments?
Explanation
Once objectives are set, you meticulously plan HOW to analyze the data (Data Analysis Plan). The data analysis plan then directly dictates exactly WHICH questions must appear on the Data Collection Instrument.
- 17
Which of the following strictly represents the correct logical and chronological sequence in the early life cycle of a planned study?
Explanation
Sequence: 1) What is the broad Question? 2) What are the specific Objectives? 3) How will we Analyze it? 4) What exact Data do we need to perform that planned analysis?
- 18
All of the following are pragmatic advantages of deliberately creating a Data Analysis Plan BEFORE collecting data EXCEPT:
Explanation
A Data Analysis plan helps you avoid collecting junk data and ensures you don't miss critical data. However, it cannot disseminate results because the data hasn't explicitly been collected or analyzed yet.
- 19
Which statement is FALSE regarding field project management?
Explanation
Infinite money cannot save a project with zero field supervision, a flawed study design, or completely untrained staff. Budget is necessary, but rigorous management and valid methodology are what generate success.
- 20
Health indicators are considered "positive" solely when they have a direct mathematical relationship (as the number increases, health status increases) with the state of health. Which is a positive indicator?
Explanation
Life expectancy going UP means health is going UP (Positive Indicator). IMR or MMR going UP means health is catastrophically going DOWN (Negative Indicator).