Topic 12 · Lift Stations & Force Mains
Set D Questions 31 to 38
- 31
Before working on a lift station pump the operator must first
Explanation
Isolating and marking the energy source is what prevents the pump starting while hands are inside it.
- 32
The static lift at a lift station is the vertical distance between the
Explanation
Friction losses are then added to this figure to arrive at the total dynamic head.
- 33
Friction loss in a force main increases most sharply with
Explanation
Loss rises roughly with the square of velocity, so an oversized pump can be surprisingly expensive to run.
- 34
Odour complaints near a lift station discharge point often result from
Explanation
Wastewater held in a full pressure pipe without oxygen turns septic and releases gas when it is released.
- 35
Chemical addition at a lift station to control odour usually targets
Explanation
Nitrate, iron salts or hypochlorite are all used to prevent or bind the sulfide before it is released.
- 36
A wet well that is far larger than needed can cause
Explanation
Wastewater sitting for hours before being pumped goes anaerobic, which creates odour and corrosion.
- 37
Recording pump run time hours at a station is useful because it
Explanation
A pump running longer for the same inflow is losing capacity, and the trend shows it before a failure.
- 38
Ventilating a wet well before entry should be done using
Explanation
A blower moving fresh air to the bottom of the space is the only reliable way to clear heavier gases.