CCO Mobile Crane Operator Exam
Crane parts, terms and signals
62 crane parts, load chart terms, safety devices, hand signals and rigging, each drawn as you'll see it on the job, with what it means.
62 parts, terms and signals
Crane Parts
Superstructure
Everything that rotates: cab, boom, hoists, engine and counterweight.
Crane Parts
Carrier
The wheeled or tracked undercarriage the superstructure turns on.
Crane Parts
Centre of rotation
The vertical axis the superstructure swings about. Every radius on the chart is measured from here.
Crane Parts
Turntable bearing
The bearing between carrier and superstructure. Its bolts are an inspection item.
Crane Parts
Counterweight
Ballast on the rear of the superstructure. Change it and the chart changes with it.
Crane Parts
Tail swing
The radius the counterweight sweeps. Barricaded under 1926.1424.
Crane Parts
Swing brake and lock
Holds the superstructure against rotation. The lock is mechanical, the brake is not.
Crane Parts
Main hoist drum
Spools the main load line. Line pull is highest on the first layer.
Crane Parts
Auxiliary hoist
Second drum, usually running the headache ball for light fast work.
Crane Parts
Boom hoist
Raises and lowers the boom. On a lattice crane it is a rope drum, on a telescopic it is a cylinder.
Crane Parts
Outrigger
Extends the machine's footprint. Charts assume fully extended and set unless they say otherwise.
Crane Parts
Float and pad
The foot on the outrigger and the pad or mat under it, spreading load into the ground.
Boom & Attachments
Telescopic boom
Sections that extend inside one another. Capacity depends on how much of each section is out.
Boom & Attachments
Lattice boom
Bolted or pinned sections of open truss. Lighter for its length and put together on the ground.
Boom & Attachments
Boom foot pin
Where the boom pivots on the superstructure. The offset from the centre of rotation belongs in every radius calculation.
Boom & Attachments
Boom point
The head of the boom, carrying the sheaves the load line runs over.
Boom & Attachments
Jib
An extension off the boom point. Comes off the capacity whether it is rigged over or stowed.
Boom & Attachments
Luffing jib
A jib whose own angle can be changed under load, unlike a fixed offset jib.
Boom & Attachments
Offset
The fixed angle a jib is pinned at to the boom centreline, commonly 2, 15 or 30 degrees.
Boom & Attachments
Pendant
Fixed-length ropes or bars carrying the boom load back to the gantry on a lattice crane.
Boom & Attachments
Gantry or A-frame
The mast the boom hoist reeving runs over, setting the angle the pendants pull at.
Boom & Attachments
Backhitch
The rear structure resisting the pull of the boom hoist reeving on a lattice machine.
Boom & Attachments
Boom deflection
The bend the boom takes under load, which grows the radius past what you set up to.
Setup & Support
Cribbing and blocking
Timber or composite built up under a float to reach firm ground or level the machine.
Setup & Support
Crane mat
A large mat spreading track or outrigger load over soft ground. Rated for bending as well as bearing.
Setup & Support
Ground bearing pressure
Load divided by bearing area. Compared against what the ground will take, which the controlling entity provides.
Setup & Support
Controlling entity
The employer with overall responsibility for the site. Under 1926.1402 the duty to provide adequate ground conditions is theirs.
Setup & Support
A/D director
Assembly and disassembly director. Meets the criteria for both a competent and a qualified person under 1926.1404.
Setup & Support
Level tolerance
How far off level the manufacturer allows, commonly within 1 percent, a little over half a degree. The chart assumes it.
Load Chart Terms
Load radius
Horizontal distance from the centre of rotation to the centre of the load, measured loaded.
Load Chart Terms
Range diagram
The side view showing what boom length and angle reach what radius and height.
Load Chart Terms
Work area diagram
The plan view showing which quadrants a capacity applies over.
Load Chart Terms
Gross capacity
The figure printed in the chart cell, before any deduction is taken off it.
Load Chart Terms
Net capacity
What is left after block, ball, jib, rope and rigging come off the gross figure.
Load Chart Terms
Bold line on a chart
Where capacity stops being limited by stability and starts being limited by structure. Above it, tipping is not the warning you get.
Load Chart Terms
Parts of line
How many falls of rope carry the block. More parts, more capacity, less hook speed.
Load Chart Terms
Quadrant of operation
Over the rear, over the side, over the front. Capacity changes between them and the lowest in the arc governs.
Safety devices and aids
Anti two-block
Stops the block being pulled up into the boom point sheaves. Required by 1926.1416.
Safety devices and aids
Load moment indicator
Reads percent of rated capacity for the configuration it has been told it is in. Tell it wrong and the number is fiction.
Safety devices and aids
Boom angle indicator
Reads the angle of the boom to horizontal. An operational aid under 1926.1416.
Safety devices and aids
Boom stop
Physically prevents the boom being raised past vertical and pulled over backwards.
Safety devices and aids
Level indicator
Tells you whether the crane is inside the manufacturer's level tolerance. Required by 1926.1415.
Hand Signals
Hoist
Forearm vertical, forefinger pointing up, hand moving in a small horizontal circle.
Hand Signals
Lower
Arm extended downward, forefinger pointing down, hand moving in a small horizontal circle.
Hand Signals
Raise boom
Arm extended, fingers closed, thumb pointing up.
Hand Signals
Lower boom
Arm extended, fingers closed, thumb pointing down.
Hand Signals
Raise boom and lower the load
Arm extended, thumb up, fingers opening and closing while the load is to move.
Hand Signals
Swing
Arm extended, forefinger pointing in the direction the boom is to swing.
Hand Signals
Stop
Arm extended, palm down, arm swung back and forth horizontally.
Hand Signals
Emergency stop
Both arms extended, palms down, swung back and forth horizontally. Anyone on site may give it.
Hand Signals
Dog everything
Hands clasped in front of the body. Stop and hold everything where it is.
Hand Signals
Travel
Arm extended forward, hand open and slightly raised, making a pushing motion in the direction of travel.
Hand Signals
Extend boom
Both fists in front of the body, thumbs pointing outward.
Hand Signals
Retract boom
Both fists in front of the body, thumbs pointing at each other.
Hand Signals
Use main hoist
Tap the fist on the head, then give the normal signal.
Hand Signals
Use auxiliary hoist
Tap the elbow with one hand, then give the normal signal.
Hand Signals
Move slowly
One hand held motionless in front of the hand giving the motion signal.
Rigging Hardware
Headache ball
Weighted overhaul ball that keeps a single part of line running down. It is a deduction, not a tool.
Rigging Hardware
Hook block
The sheaved block the load line reeves through. Its weight comes off the chart every time.
Rigging Hardware
Spreader bar
Holds the sling legs apart to keep the angle up and the compression out of the load.
Rigging Hardware
Tagline
The line a ground worker uses to control a load without standing under it.
Rigging Hardware
Shackle
Pin-and-bow connector. Loaded on the bow, never sideways, and always with the pin secured.
Names for the same part vary between manufacturers; the crane's own manual and load chart always win.