Crane parts, terms and signals

62 crane parts, load chart terms, safety devices, hand signals and rigging, each drawn as you'll see it on the job, with what it means.

62 parts, terms and signals

  • Crane Parts

    Superstructure

    Everything that rotates: cab, boom, hoists, engine and counterweight.

  • Crane Parts

    Carrier

    The wheeled or tracked undercarriage the superstructure turns on.

  • Crane Parts

    Centre of rotation

    The vertical axis the superstructure swings about. Every radius on the chart is measured from here.

  • Crane Parts

    Turntable bearing

    The bearing between carrier and superstructure. Its bolts are an inspection item.

  • Crane Parts

    Counterweight

    Ballast on the rear of the superstructure. Change it and the chart changes with it.

  • Crane Parts

    Tail swing

    The radius the counterweight sweeps. Barricaded under 1926.1424.

  • Crane Parts

    Swing brake and lock

    Holds the superstructure against rotation. The lock is mechanical, the brake is not.

  • Crane Parts

    Main hoist drum

    Spools the main load line. Line pull is highest on the first layer.

  • Crane Parts

    Auxiliary hoist

    Second drum, usually running the headache ball for light fast work.

  • Crane Parts

    Boom hoist

    Raises and lowers the boom. On a lattice crane it is a rope drum, on a telescopic it is a cylinder.

  • Crane Parts

    Outrigger

    Extends the machine's footprint. Charts assume fully extended and set unless they say otherwise.

  • Crane Parts

    Float and pad

    The foot on the outrigger and the pad or mat under it, spreading load into the ground.

  • Boom & Attachments

    Telescopic boom

    Sections that extend inside one another. Capacity depends on how much of each section is out.

  • Boom & Attachments

    Lattice boom

    Bolted or pinned sections of open truss. Lighter for its length and put together on the ground.

  • Boom & Attachments

    Boom foot pin

    Where the boom pivots on the superstructure. The offset from the centre of rotation belongs in every radius calculation.

  • Boom & Attachments

    Boom point

    The head of the boom, carrying the sheaves the load line runs over.

  • Boom & Attachments

    Jib

    An extension off the boom point. Comes off the capacity whether it is rigged over or stowed.

  • Boom & Attachments

    Luffing jib

    A jib whose own angle can be changed under load, unlike a fixed offset jib.

  • Boom & Attachments

    Offset

    The fixed angle a jib is pinned at to the boom centreline, commonly 2, 15 or 30 degrees.

  • Boom & Attachments

    Pendant

    Fixed-length ropes or bars carrying the boom load back to the gantry on a lattice crane.

  • Boom & Attachments

    Gantry or A-frame

    The mast the boom hoist reeving runs over, setting the angle the pendants pull at.

  • Boom & Attachments

    Backhitch

    The rear structure resisting the pull of the boom hoist reeving on a lattice machine.

  • Boom & Attachments

    Boom deflection

    The bend the boom takes under load, which grows the radius past what you set up to.

  • Setup & Support

    Cribbing and blocking

    Timber or composite built up under a float to reach firm ground or level the machine.

  • Setup & Support

    Crane mat

    A large mat spreading track or outrigger load over soft ground. Rated for bending as well as bearing.

  • Setup & Support

    Ground bearing pressure

    Load divided by bearing area. Compared against what the ground will take, which the controlling entity provides.

  • Setup & Support

    Controlling entity

    The employer with overall responsibility for the site. Under 1926.1402 the duty to provide adequate ground conditions is theirs.

  • Setup & Support

    A/D director

    Assembly and disassembly director. Meets the criteria for both a competent and a qualified person under 1926.1404.

  • Setup & Support

    Level tolerance

    How far off level the manufacturer allows, commonly within 1 percent, a little over half a degree. The chart assumes it.

  • Load Chart Terms

    Load radius

    Horizontal distance from the centre of rotation to the centre of the load, measured loaded.

  • Load Chart Terms

    Range diagram

    The side view showing what boom length and angle reach what radius and height.

  • Load Chart Terms

    Work area diagram

    The plan view showing which quadrants a capacity applies over.

  • Load Chart Terms

    Gross capacity

    The figure printed in the chart cell, before any deduction is taken off it.

  • Load Chart Terms

    Net capacity

    What is left after block, ball, jib, rope and rigging come off the gross figure.

  • Load Chart Terms

    Bold line on a chart

    Where capacity stops being limited by stability and starts being limited by structure. Above it, tipping is not the warning you get.

  • Load Chart Terms

    Parts of line

    How many falls of rope carry the block. More parts, more capacity, less hook speed.

  • Load Chart Terms

    Quadrant of operation

    Over the rear, over the side, over the front. Capacity changes between them and the lowest in the arc governs.

  • Safety devices and aids

    Anti two-block

    Stops the block being pulled up into the boom point sheaves. Required by 1926.1416.

  • Safety devices and aids

    Load moment indicator

    Reads percent of rated capacity for the configuration it has been told it is in. Tell it wrong and the number is fiction.

  • Safety devices and aids

    Boom angle indicator

    Reads the angle of the boom to horizontal. An operational aid under 1926.1416.

  • Safety devices and aids

    Boom stop

    Physically prevents the boom being raised past vertical and pulled over backwards.

  • Safety devices and aids

    Level indicator

    Tells you whether the crane is inside the manufacturer's level tolerance. Required by 1926.1415.

  • Hand Signals

    Hoist

    Forearm vertical, forefinger pointing up, hand moving in a small horizontal circle.

  • Hand Signals

    Lower

    Arm extended downward, forefinger pointing down, hand moving in a small horizontal circle.

  • Hand Signals

    Raise boom

    Arm extended, fingers closed, thumb pointing up.

  • Hand Signals

    Lower boom

    Arm extended, fingers closed, thumb pointing down.

  • Hand Signals

    Raise boom and lower the load

    Arm extended, thumb up, fingers opening and closing while the load is to move.

  • Hand Signals

    Swing

    Arm extended, forefinger pointing in the direction the boom is to swing.

  • Hand Signals

    Stop

    Arm extended, palm down, arm swung back and forth horizontally.

  • Hand Signals

    Emergency stop

    Both arms extended, palms down, swung back and forth horizontally. Anyone on site may give it.

  • Hand Signals

    Dog everything

    Hands clasped in front of the body. Stop and hold everything where it is.

  • Hand Signals

    Travel

    Arm extended forward, hand open and slightly raised, making a pushing motion in the direction of travel.

  • Hand Signals

    Extend boom

    Both fists in front of the body, thumbs pointing outward.

  • Hand Signals

    Retract boom

    Both fists in front of the body, thumbs pointing at each other.

  • Hand Signals

    Use main hoist

    Tap the fist on the head, then give the normal signal.

  • Hand Signals

    Use auxiliary hoist

    Tap the elbow with one hand, then give the normal signal.

  • Hand Signals

    Move slowly

    One hand held motionless in front of the hand giving the motion signal.

  • Rigging Hardware

    Headache ball

    Weighted overhaul ball that keeps a single part of line running down. It is a deduction, not a tool.

  • Rigging Hardware

    Hook block

    The sheaved block the load line reeves through. Its weight comes off the chart every time.

  • Rigging Hardware

    Spreader bar

    Holds the sling legs apart to keep the angle up and the compression out of the load.

  • Rigging Hardware

    Tagline

    The line a ground worker uses to control a load without standing under it.

  • Rigging Hardware

    Shackle

    Pin-and-bow connector. Loaded on the bow, never sideways, and always with the pin secured.

Names for the same part vary between manufacturers; the crane's own manual and load chart always win.