- 1
The CCO specialty designation LBC covers which type of crane?
Explanation
LBC is lattice boom crawler. LBT is lattice boom truck, and the two telescopic designations are TLL and TSS.
- 2
The CCO specialty designation LBT covers which type of crane?
Explanation
LBT is the lattice boom machine mounted on a wheeled carrier, as distinct from the crawler mounted LBC.
- 3
What raises and lowers the boom on a lattice crane?
Explanation
Lattice machines luff the boom with rope. Telescopic machines use a hydraulic lift cylinder, which is one of the main differences between the two families.
- 4
What is the function of boom pendants on a lattice crane?
Explanation
Pendants are fixed length ropes or bars running from the boom point back to the gantry. Their length must match the boom being used.
- 5
Why must pendant lengths match the boom length in use?
Explanation
Pendants are the load path holding the boom up. Wrong lengths change the angle they pull at and put the structure outside its design.
- 6
What is the gantry on a lattice crane used for?
Explanation
The gantry sets the angle the boom hoist reeving pulls at. A raised gantry gives better leverage on the boom, particularly at low boom angles.
- 7
On a lattice crane, what does the backhitch do?
Explanation
The backhitch is part of the structure holding the boom up. It is a specific item on the annual comprehensive inspection.
- 8
What is a lattice boom made of?
Explanation
The open truss gives a lattice boom a very high strength to weight ratio, which is why lattice machines reach far greater lengths than telescopic ones.
- 9
What is the main advantage of a lattice boom over a telescopic boom?
Explanation
The weight saving is the whole point. It is also the reason a lattice boom has to be built up on the ground and cannot be extended from the cab.
- 10
What is the main disadvantage of a lattice boom compared with a telescopic boom?
Explanation
A telescopic boom is ready to work on arrival. A lattice boom needs an assembly crew, an assembly area and time at both ends of the job.