Topic 12 · Nonpotable Water Systems
Set B Questions 11 to 20
- 11
Rainwater filter particle size:
Explanation
Rainwater systems mandate 100-micron or finer filtration to prevent UV lamp degradation.
- 12
Cross-connection test procedure:
Explanation
Cross-connection testing pressurizes one system while bleeding the other in both directions.
- 13
Pipes in same trench spacing:
Explanation
Nonpotable contamination risk requires strict separation analogous to sewer-to-water clearances.
- 14
First-flush diverter purpose:
Explanation
First-flush diverts initial roof runoff containing pollutants away from storage cistern.
- 15
Overflow pipe termination design:
Explanation
Overflows must terminate openly with fine mesh screening to prevent mosquito breeding.
- 16
Above-ground tank material:
Explanation
Sunlight fuels algae; tanks must be opaque or buried to prevent biological hazard.
- 17
Underground tank vent location:
Explanation
Tank vents must terminate above grade with fine screening to prevent vermin entry.
- 18
Potable makeup termination method:
Explanation
IPC 1301.5: Potable pipe must terminate above overflow rim as air gap to prevent siphonage.
- 19
Untreated gray water retention:
Explanation
IPC 1302.2: Untreated systems must irrigate immediately or discharge within 24 hours.
- 20
Failing gray water failsafe:
Explanation
Gray water systems must fail safely by bypassing directly to sanitary main.