Topic 01 · Scope & Administration
Set E Questions 41 to 50
- 41
If a trench is dug too close to the load-bearing angle of a foundation wall, what is the required remedy?
Explanation
If a trench compromises the 45-degree bearing plane of a footing, it must be backfilled with concrete to properly transfer and support the structural load.
- 42
For PEX tubing, hangers must be sized:
Explanation
IPC 308.3: Hangers for plastic tubing like PEX must easily permit sliding without compressing or deforming the tubing.
- 43
What is the required maximum hanger spacing for 2-inch PVC pipe running vertically?
Explanation
IPC Table 308.5: Vertical PVC requires base and floor-level support, standardly summarized as 10-foot maximum intervals, utilizing mid-story guides.
- 44
An underground water service pipe made of copper passes through a concrete foundation wall. The space between the pipe and sleeve must be:
Explanation
IPC 305.5: Annular spaces between sleeves and pipes through exterior walls/foundations must be sealed with caulking, mastic, or approved sealant.
- 45
Can you use a steel wire to strap up PVC drainage tubing?
Explanation
IPC 308.2: Hanger metal directly impacting plastic pipe is prohibited if it risks cutting, scratching or point-loading. Flat strapping or wide plastic/metal clevis hangers are required.
- 46
The water distribution pipe passing through concrete to a floor-mounted bathtub valve requires:
Explanation
IPC 305.1: Any piping embedded in or passing through concrete requires a protective sleeve or wrapping to prevent chemical degradation or shifting stress.
- 47
Which of these hanger types is generally considered the standard for supporting heavy horizontal runs of cast iron or steel pipe?
Explanation
A clevis hanger suspended by threaded rod anchored structurally is the industry standard for distributing heavy loads of metallic piping.
- 48
When supporting continuous horizontal runs of CPVC in a hot water system, one must be cautious to provide:
Explanation
IPC 308.3: Plastics like CPVC undergo massive thermal expansion compared to metal; they require expansion loops to absorb the growth without warping or breaking.
- 49
What governs the size and embedding depth of a threaded rod anchor/insert shot into a concrete ceiling?
Explanation
Anchor ratings and threaded rod sizes correspond to the maximum calculated structural load (weight of the pipe plus water), conforming to engineering specifications and manufacturer limits.
- 50
When installing flexible tubing like CSST or PEX with sweeping bends, the spacing of hangers around these bends must:
Explanation
Flexible piping making sweeping bends requires careful support to maintain the radius and prevent kinking (following manufacturer spacing rules, often requiring support near the apex).