Inspection Limits

Removal criteria, temperature limits and clearances, straight from 29 CFR. Any one of the removal conditions takes the sling out of service on the spot — they are not a scale.

Wire rope sling — removal from service

29 CFR 1910.184(f)(5)

ConditionLimit
Randomly distributed broken wires10 in one rope lay
Broken wires in one strand5 in one rope lay
Wear on outside wiresOver 1/3 of original diameter
Kinking, crushing, bird cagingAny occurrence
Heat damageAny evidence
End attachmentsCracked, deformed or worn
Hook throat openingOver 15% of original
Hook twist out of planeOver 10 degrees
CorrosionAny, of rope or end attachments

Synthetic web sling — removal from service

29 CFR 1910.184(i)(9)

  • Acid or caustic burns.
  • Melting or charring of any part of the surface.
  • Snags, punctures, tears or cuts.
  • Broken or worn stitching.
  • Distortion of fittings.

Safe operating temperatures

29 CFR 1910.184(e) and (i)

Sling typeLimit
Alloy steel chainDerate above 600 °F per maker
Alloy steel chainRemove permanently above 1,000 °F
Nylon webNot above 180 °F
Polyester webNot above 180 °F
Polypropylene webNot above 200 °F

Minimum power line clearance

29 CFR 1926 Subpart CC

Line voltageMinimum clearance
Up to 50 kV10 ft
Over 50 to 200 kV15 ft
Over 200 to 350 kV20 ft
Over 350 to 500 kV25 ft
Over 500 to 750 kV35 ft
Over 750 to 1,000 kV45 ft

Where the voltage is unknown, assume the larger distance. A line is energised until the utility says otherwise.

Proof test requirements

29 CFR 1910.184 and 1926.251

ItemProof test
New or repaired chain slingBy maker or equivalent
Metal mesh sling1.5 × rated capacity
Repaired synthetic web sling2 × rated capacity
Custom fabricated accessory1.25 × rated capacity

Fibre rope splices

29 CFR 1910.184(h)

RopeEye spliceShort splice
Manila3 full tucks6 full tucks
Synthetic fibre4 full tucks8 full tucks