Topic 07 · Crane Capacity Basics
Set C Questions 21 to 30
- 21
How does being out of level affect capacity?
Explanation
Even a degree or two out of level can cost a large fraction of capacity at long radius, because the boom swings out further than intended.
- 22
What does a jib do to crane capacity?
Explanation
A jib adds weight and length out at the boom tip. Many charts require a deduction for a jib even when it is stowed alongside the boom.
- 23
What is parts of line?
Explanation
More parts of line share the load between more rope parts, raising the hoist capacity, though it slows the hoist speed.
- 24
What limits capacity when too few parts of line are reeved?
Explanation
The chart may allow more than the reeving can carry. Line pull capacity must be checked separately from chart capacity.
- 25
What is the difference between a duty cycle and a lift crane rating?
Explanation
Repetitive work such as clamshell or dragline duty is derated because of the fatigue and dynamic loading involved.
- 26
What does a load chart note about wind normally say?
Explanation
Charts are valid up to a stated wind speed, often around 20 mph. Above that the manufacturer procedure governs.
- 27
A crane has a net capacity of 10,000 lb and the load is 9,500 lb. What does this indicate?
Explanation
It is within capacity but has almost no margin for wind, shock or an underestimated weight. Most employers require a lift plan at this level.
- 28
What is the overturning moment of a crane load?
Explanation
Weight times distance is what tries to tip the machine. Doubling the radius doubles the moment for the same load.
- 29
A boom is 120 ft long and the target radius is 60 ft with no boom foot offset. What boom angle is needed?
Explanation
The cosine of the angle is 60 over 120, which is 0.5, so the angle is 60 degrees.
- 30
Why is the weight of the hook block a deduction?
Explanation
The boom cannot tell the difference between block weight and load weight. Both create the same overturning moment.