Topic 06 · Load Control & Lift Planning
Set D Questions 31 to 40
- 31
Why are multi-crane lifts derated?
Explanation
Small differences in hoist speed or ground settlement transfer load from one crane to the other, so a margin is planned in.
- 32
When may personnel be lifted by a crane?
Explanation
Lifting people is tightly regulated, with a purpose-built platform, heavy derating and a trial lift among the requirements.
- 33
What is the pre-lift meeting for?
Explanation
Everyone involved agrees what will happen, who signals, and what stops the job. It is the cheapest safety measure available.
- 34
What should be done if conditions change mid-lift?
Explanation
A plan made for different conditions no longer applies. Wind, ground and load changes all justify stopping.
- 35
What is the effect of a load contacting an obstruction while being hoisted?
Explanation
The load hangs up, tension builds, and when it frees the stored energy arrives suddenly. Hoisting stops the moment contact is noticed.
- 36
How is the swing of a load best minimised?
Explanation
A load is a pendulum, and abrupt starts and stops are what set it swinging. Gentle motion keeps it under the hook.
- 37
What must be verified about the ground before a load is landed?
Explanation
A load that settles unevenly can topple after the rigging is released. Blocking spreads the pressure onto sound ground.
- 38
What is the purpose of barricading the lift area?
Explanation
The barricade defines the area where a dropped load or dropped object would land, and keeps uninvolved people out of it.
- 39
A 2,000 lb load must be held 10 degrees off vertical. Roughly what tag line pull is needed?
Explanation
The tangent of 10 degrees is 0.176, so 2,000 times 0.176 is about 353 lb. That is well beyond a single person on a rope.
- 40
What is the rule about riding on a load or a hook?
Explanation
People are lifted only in an approved personnel platform under the specific rules for that operation. Riding the load or the ball is never acceptable.