Topic 10 · Regulations & Responsibilities
Set B Questions 11 to 20
- 11
What does OSHA require about makeshift fasteners in rigging?
Explanation
Makeshift links or fasteners formed from bolts or rods, or other such attachments, are explicitly prohibited.
- 12
What is required of attachments used with an alloy steel chain sling?
Explanation
If an attachment is rated lower, the whole assembly is limited to the capacity of that weakest component.
- 13
How often must slings be inspected under the standard?
Explanation
Daily or shift inspection by a competent person is the baseline, with thorough periodic inspections at intervals set from service experience.
- 14
Who determines the interval for periodic sling inspections?
Explanation
The standard sets the basis, which is experience of service life in similar circumstances, rather than a fixed calendar period.
- 15
What must happen to a damaged or defective sling?
Explanation
Removal is immediate and not conditional. Repairs are made only by the manufacturer or an equivalent entity.
- 16
What is the minimum clearance from an energised line up to 50 kV?
Explanation
Ten feet is the baseline in the construction crane rules, with greater distances required as voltage rises above 50 kV.
- 17
What must the employer do before crane work near power lines?
Explanation
The work zone is determined, lines are identified, and either the minimum clearance is maintained or the line is de-energised and grounded.
- 18
What are the requirements for a qualified signalperson?
Explanation
They must know the signals, understand crane operation and dynamics, know the requirements, and have been assessed by a qualified evaluator.
- 19
Where must signalperson qualification documentation be available?
Explanation
It has to be available at the site so it can be produced during the work rather than retrieved afterwards.
- 20
Who has final authority to stop a lift?
Explanation
The operator has authority to stop and refuse to handle loads until safety is assured. Anyone may give a stop signal.