Load Charts & Capacity

Load charts are the largest single block on the certification. They are 26% of the Core exam and 35% of every Specialty exam, which together is more than any other subject. Everything on a chart comes back to one relationship: the further out the load sits from the centre of rotation, the less the crane can lift.

What it covers

Reading a rated capacity chart, the range diagram and the work area diagram, deductions, net capacity, percent of chart, quadrants of operation, and the conditions a chart assumes about the machine.

On the exam

Expect worked problems as well as concept questions. You will be given a chart figure and a set of deductions and asked what the load may weigh. On the Core exam you do that arithmetic without a calculator.

How to prepare

Learn the deductions first, because that is where the exam concentrates. Then learn what changes which chart: boom length, boom angle, counterweight, outrigger position and quadrant each move you to a different set of numbers.

  • Gross capacity - the figure printed in the chart cell, before anything is taken off it.
  • Net capacity - what is left once block, ball, jib, rope and rigging are deducted.
  • Load radius - the horizontal distance from the centre of rotation to the centre of the load.
  • Range diagram - the side view, showing what boom length and angle reach what radius and height.
  • Work area diagram - the plan view, showing which quadrants a capacity applies over.
  • Bold line - where the chart stops being limited by stability and becomes limited by structure.
  • Parts of line - the number of falls of rope carrying the block.

How to attack this topic

  • Deductions come off the capacity. They are not added to the load. Both routes agree on whether the lift is legal, and only the first tells you how much load you have left.
  • A stowed jib is still a deduction. It is dead weight on the boom whether it is rigged over or folded alongside, and treating it as weightless is a classic overload.
  • When the radius falls between two rows, take the next longer radius, and between two boom lengths take the lower capacity of the two. Most manufacturers state that chart values are not to be interpolated.
  • Above the bold line the crane will not warn you. Below it the machine gets light before it goes over. Above it a component fails with no warning at all.
  • A lift that swings through more than one quadrant is planned to the lowest capacity it will pass over, not the one it is picked up in.