Loading Rates

A settling basin's surface loading, weir overflow rate and rise rate from the plant flow, the weir length and the surface area.

Surface loading

400 gpd/sq ft

Weir 16,667 gpd/ft | Rise 0.037 ft/min

Weir rate within the range most plants design to.

How it's worked out

Weir rate = Q / weir length, Surface loading = Q / surface area

  1. Convert flow to gallons per day2.00 MGD x 1,000,000= 2,000,000 gal/day
  2. Weir overflow rate2,000,000 gal/day / 120.0 ft= 16,667 gpd/ft
  3. Surface loading rate2,000,000 gal/day / 5,000 sq ft= 400 gpd/sq ft
  4. Rise rate - surface loading per minute, over 7.480.278 gal/min/sq ft / 7.48= 0.037 ft/min