Skip to content

Crane Capacity Basics

Rigger Level II material, and the place where rigging meets the machine. Capacity is governed by load times radius, deductions come off the capacity rather than on to the load, and the chart that matters is the one for this crane in this configuration. Get those three ideas right and most of the topic follows.

What it covers

Load radius, gross and net capacity, deductions, boom geometry, outriggers and ground bearing, quadrants of operation, and what the load chart does and does not tell you.

On the exam

Expect a net capacity calculation and at least one boom geometry question using sine and cosine. Deductions taken the wrong way round is the classic wrong answer.

How to prepare

Practise the net capacity sequence until it is automatic: add the deductions, subtract from gross, compare the bare load against what is left.

How to attack this topic

  • Deductions come off the capacity. If you also add them to the load you have counted them twice, and that distractor is always on offer.
  • Cosine gives horizontal reach, sine gives height. Mixing them up is easy under time pressure and produces an answer that looks plausible.
  • Capacity falls faster than radius rises, because stability governs at reach. A shorter radius is the cheapest capacity you can buy.
  • The geometric radius is never the real radius. Boom deflection always makes it larger.