Tools
Sludge Age
Pounds of MLSS in aeration over the pounds of suspended solids applied each day, the simpler cousin of MCRT.
Sludge age
7.8 days
Sludge age and MCRT answer similar questions but are not the same number. Keep the inputs distinct: sludge age uses influent solids, MCRT uses solids actually leaving the plant.
How it's worked out
Sludge Age = (lbs MLSS in aeration) / (lbs suspended solids applied per day)
- Pounds of MLSS in the aeration tank0.750 MG x 2,500 mg/L x 8.34= 15,638 lbs
- Pounds of solids applied per day2.00 MGD x 120.0 mg/L x 8.34= 2,002 lbs/day
- Divide the inventory by the daily load15,638 / 2,002= 7.8 days