Critical Lift Check
Whether a lift meets any of the usual critical-lift triggers: 75 percent of chart, two cranes, people on the hook, a blind pick, work over occupied space or an engineered lift.
This lift is
Routine lift
No critical-lift trigger met
One trigger is enough. The 75% figure is an industry and employer trigger, widely used and written into most site lift-plan procedures, but it is not in OSHA Subpart CC. Hoisting personnel is different: that one is federal, at 29 CFR 1926.1431. Your employer's procedure may set a lower threshold and it governs.
How it's worked out
Critical lift = any one trigger, not all of them
- Percent of chart60.0% against a 75% trigger= Below the trigger