Whether a lift meets any of the usual critical-lift triggers: 75 percent of chart, two cranes, people on the hook, a blind pick, work over occupied space or an engineered lift.

More than one crane on the load
Hoisting personnel
Blind pick
Over occupied space or live equipment
Non-routine or engineered

This lift is

Routine lift

No critical-lift trigger met

One trigger is enough. The 75% figure is an industry and employer trigger, widely used and written into most site lift-plan procedures, but it is not in OSHA Subpart CC. Hoisting personnel is different: that one is federal, at 29 CFR 1926.1431. Your employer's procedure may set a lower threshold and it governs.

How it's worked out

Critical lift = any one trigger, not all of them

  1. Percent of chart60.0% against a 75% trigger= Below the trigger

The other twenty-eight tools