Quadrant of Operation

The capacity that governs a swing through more than one quadrant: the lowest one the load passes over, not the one it was picked up in.

Passes over the rear
Passes over the side
Passes over the front

Capacity used

40.9% of capacity

Governed over the side at 22,000 lb

Capacity changes as the crane swings because the machine is only as stable as the narrowest direction it is leaning in. Over the front is usually the weakest on a truck crane, because the tipping line sits closest to the centre of rotation there, and 29 CFR 1926.1417(r) forbids lifting over the front of wheel-mounted equipment unless the manufacturer permits it. Picking a load in a strong quadrant and swinging it into a weak one can cause a tip-over: the capacity that governs is the lowest one the load will pass over, and the figure shown above is worked that way.

How it's worked out

The lowest capacity in the swing arc governs the whole lift

  1. Chart capacity over the rearhigher than the governing figure= 30,000 lb
  2. Chart capacity over the sidelowest in the arc= 22,000 lb
  3. Plan the lift to the lowest figure in the arc9,000 lb / 22,000 lb x 100= 40.9%
  4. Working to the best quadrant instead would read9,000 lb / 30,000 lb x 100= 30.0%