Skip to content

Out of Level

The extra radius a crane picks up when it is not level, worked from the boom length and angle, to look up on your own chart.

Radius gained

+0.76 ft of radius

Working radius goes from 50.0 ft to 50.8 ft

This tool will not tell you a percentage of capacity lost, and no honest tool can. That figure depends on boom length, boom angle and where you sit on the capacity curve, and the numbers the trade repeats for it span five percent to fifty percent for the same tilt. What is certain is the extra radius, and it is worked out above. Look 50.8 ft up on your own chart and read the capacity there. Then level the crane anyway.

How it's worked out

Radius gained = boom point height above the pivot x tan(tilt)

  1. How high the boom point sits above the boom foot pin100.0 ft x sin(60.0°)= 86.60 ft
  2. How far the boom point leans out over the low side86.60 ft x tan(0.5°)= 0.76 ft
  3. Radius you must now read on the chart50.0 ft + 0.76 ft= 50.76 ft
  4. As a share of the level radius0.76 / 50.00 x 100= 1.5% more radius

The other twenty-eight tools