Parts of Line Needed
How many parts of line a load needs at the permissible line pull, always rounded up, with sheave friction if you want it.
Reeve
4 parts of line
Holds 44,000 lb at this line pull
Rounding down understates the required parts of line. More parts of line buys capacity and costs hook speed, so an operator who needs to move fast will always be tempted to reeve one part short. The permissible line pull is the lower of what the rope will take and what the drum and machinery will pull, and on the first layer of the drum it is usually the machinery.
How it's worked out
Parts = load / permissible line pull, always rounded up
- Divide the load by what one part will pull40,000 lb / 11,000 lb= 3.636
- Round up. There is no such thing as a part of a part3.636 rounded up= 4 parts