The load as a percentage of the net capacity, with the margin left, the quick check against an LMI reading.
Capacity used
50.0% of capacity
12,000 lb left before the chart runs out
An LMI reads percent of the configuration it has been told it is in. If the configuration set in the LMI is not the configuration the crane is actually rigged in, the percentage is fiction. Check it against the chart by hand before the first pick.
How it's worked out
Percent of chart = Total load / Net capacity x 100
- Divide the load by what the crane is rated for12,000 lb / 24,000 lb= 0.500
- Express it as a percentage0.500 x 100= 50.0%
- Margin remaining24,000 lb - 12,000 lb= 12,000 lb