Tools
Installation Check
The checks that decide whether an assembly can be tested at all, and whether it would protect anything if it were.
Height above the outlets (PVB, SVB)
- A PVB or SVB must sit at least twelve inches above the highest downstream outlet, measured to the bottom of the assembly.
- Why: The air inlet has to break the siphon. Below the outlets there is nothing for it to break.
Height above grade (all four)
- Twelve inches from the floor or grade to the bottom of the assembly is the usual minimum, and thirty inches is the usual maximum to the centre line.
- Why: Low enough to work on, high enough that the relief port is not sitting in a puddle it can siphon back.
Relief port discharge (RP)
- An RP relief port discharges to atmosphere through an air gap. It is never directly connected to a drain.
- Why: A direct connection makes the drain itself the cross-connection you were hired to eliminate.
Never in a pit that can flood (RP)
- An RP may not go in a pit or vault where the relief port could be submerged.
- Why: A submerged relief port cannot vent, and it can siphon whatever is in the pit.
Orientation (all four)
- Fit the assembly the way it is approved. Most are horizontal only, and the approval is for the position as much as the model.
- Why: A vertical installation of a horizontal-only assembly changes how the poppets seat and voids the approval.
Clearance for testing (all four)
- Enough room to get a gauge and two hands onto every test cock, and to remove the covers.
- Why: An assembly that cannot be tested is an assembly that will not be, and it stops being protection the year after it goes in.
Freeze protection (all four)
- Protect from freezing without blocking access or the relief port.
- Why: A burst assembly is an open cross-connection, and heat tape wrapped over a relief port is worse than no heat tape.
Approved assembly for the hazard (all four)
- Confirm the assembly fitted is the one the hazard calls for before you test it.
- Why: A passing test on the wrong assembly still leaves the water unprotected, and your name is on the report.
The other twenty-three tools
Paperwork
The test
- DC Test WalkthroughStep by step, at the assembly
- RP Test WalkthroughStep by step, at the assembly
- PVB Test WalkthroughStep by step, at the assembly
- SVB Test WalkthroughStep by step, at the assembly
- RP Pass or FailReadings judged against the rule
- DC Pass or FailReadings judged against the rule
- PVB / SVB Pass or FailReadings judged against the rule
- Gauge ElevationCorrecting for where it hangs