SVB Test Walkthrough

The spill-resistant vacuum breaker test, one step at a time: the check valve first through the vent valve, then the air inlet.

The same two criteria as a PVB, tested in the opposite order. The check valve comes first here, because the vent valve lets you drop the body to atmosphere without spilling, which is the whole point of the design.

Phase 1 of 4 · step 1 of 5 in this phase · 1 of 19

Preparation

Set up so the readings mean something and nobody is surprised by the water going off.

Tell the customer the supply is about to be shut off.

Why this step exists

A test isolates the service. Doing that unannounced to a restaurant at noon or a dialysis clinic at any hour is how testers lose accounts.

See every step at once
  1. Preparation

    Set up so the readings mean something and nobody is surprised by the water going off.

    1. Tell the customer the supply is about to be shut off.
    2. Look over the installation before touching anything.An assembly installed backwards will produce readings that look like component failures.
    3. Flush the test cocks. Open 4, then 3, then 2, then 1, and close them in the reverse order, 1, 2, 3, 4.Skipping this is the fastest way to need a gauge recalibration you did not budget for.
    4. Fit the adapters and check the kit over.
    5. Close every needle valve on the kit.
  2. Test 1, the check valve

    Measure the static drop across the check first, using the vent valve rather than a spilling test cock.

    1. Take the air inlet canopy off.
    2. Fit a bleed-off valve to the test cock and run the high hose from it to the kit, then open the test cock.
    3. Purge the high side, then close the high bleed.
    4. With the kit level with the vent valve, close the number 2 shut-off, then the number 1 shut-off.
    5. Open the vent valve, or back out the vent screw.
    6. When water stops draining from the vent, read the differential.Record: Check valve differential, 1.0 psid or higher
    7. If water keeps running from the vent at more than a drip, open the bleed-off slowly until it is down to a drip, then read. If it cannot be stopped, the number 1 shut-off needs work.
  3. Test 2, the air inlet

    Find where the air inlet opens, without moving the kit.

    1. Keep the kit at the level of the vent valve.Moving it between the two tests introduces an elevation error into the second reading.
    2. Open the high bleed slowly, no more than a quarter turn.
    3. Read the pressure at the instant the air inlet opens.Record: Air inlet opening point, 1.0 psi or higher to pass
    4. Close the high bleed, take the hose off the bleed-off to drain the body, and confirm the air inlet opens fully.Record: Air inlet opened fully, yes or no
  4. Return to service

    Leave the assembly and the kit the way you found them.

    1. Close the test cock and the vent valve or refit the vent screw.
    2. Open shut-off 1, then open shut-off 2 slowly.Upstream first. Opening the downstream valve first can pull the body down and lift the air inlet.
    3. Refit the canopy and drain the kit.

What the readings have to meet

  • Check valve: Holds 1.0 psid or higher ASSE 1056
  • Air inlet: Begins to open at 1.0 psi or higher above atmosphere, and opens fully at atmospheric pressure ASSE 1056

Procedures differ between test kits and between water purveyors. This is the widely taught differential gauge sequence. Confirm the procedure your own authority accepts before you use it on a report.